We specialize in value engineering, working together to find the most cost-effective, safe, and timely way to meet project challenges.

We’ve built the continent’s three longest cable-stayed bridges, the world’s first stress-ribbon bridge and a segmental bridge with the largest precast segments in the world. Flatiron’s in-house engineers have decades of experience devising innovative solutions for complex construction issues on major infrastructure projects.

Flatiron engineers develop innovative construction methods using cofferdams, trestles, floating concrete tubs, scaffold, formwork, trusses, and gantries. We lift, lower, push, and erect massive elements using a wide range of methods, equipment and materials. From complicated critical crane picks using land-based cranes and floating cofferdams to synchronous raising and lowering, cofferdams and stiff-legged derricks, Flatiron’s engineers derive solutions for any complex scenario.

Flatiron Engineering Solutions

Our engineering expertise has allowed us to build some of the most innovative projects in North America.

Washington Bypass

North Carolina

Challenge:

A three-mile long bridge over environmentally sensitive wetlands and the Pamlico-Tar River.

Solution:

Flatiron developed innovative construction methods to reduce environmental impacts using a Tilting Lead Gantry. Flatiron developed and patented (U.S. Patent No. 7,520,014 B2) a top-down construction technique to ensure minimal disturbance to the surrounding environment. This span-by-span construction method used the newly constructed permanent structure for personnel access and material deliveries.

The process consisted of self-contained gantries capable of performing all tasks associated with the bridge construction, including driving the precast piles, building the bent caps, erecting the 120-foot-long precast girders, and pouring the deck. All of these operations were performed without the use of temporary access trestles, thus significantly reducing environmental disturbances.

This method required designing and manufacturing a specialized piece of equipment—a launching gantry designed and supplied by Deal of Italy with special pile driving equipment designed by Bermingham of Canada—never used before to actually drive pile from the cantilevered end of the gantry.

Kicking Horse Pass

British Columbia

Challenge:

A curved bridge over a very steep canyon through the Canadian Rocky Mountains.

Solution:

This was the first incrementally launched bridge on a curve.

The girder launching process involved launching four main steel girders uphill from west to east using a hydraulic launch system that erects two girder pairs one span at a time until the total length has been launched. The team erected the girder pairs in a 410-foot launching bed located behind the west abutment that had been graded at 6 percent with a curve to match the profile of the bridge. The team erected each girder pair, along with all the cross frames and lateral bracing, on the launching bed. The team then launched two girders approximately 250 feet to the next pier where they rested while the next two pairs were erected and launched.

John James Audubon Bridge

Louisiana

Challenge:

Longest cable-stayed bridge in North America; bridge over the Mississippi River.

Solution:

Flatiron engineers developed a complex 48-point synchronous lowering system for the John James Audubon cable-stayed bridge. Because the Mississippi River is fast and deep, Flatiron chose to construct the cofferdam above the river and lowering it using a jacking system.

About 10,000 feet of hydraulic hoses were used to run the jacking system that lowered the 2,500-ton cofferdams (one each on the east and west sides) into the river. To ensure the system and process ran smoothly workers did a mock-up of the cofferdam in a nearby lay down yard.

Port Mann Bridge

British Columbia

Challenge:

Construction of the longest cable-stayed bridge in North America (at time of construction).

Largest drilled shaft static load test ever performed in the world.

Solution:

Flatiron planned the framework and template to support the 20 stay tubes and the rebar for the S1 Pylon Knuckle.

The Vigintipod was designed to support all 20 stay tubes and 75 percent of all the rebar in the knuckle, and could be split down the middle so the tower crane could have the capacity to place each half. It was picked and installed 400 feet up in the air.

The total pick weight was just over 70,000 lbs, which was about 90 percent overall capacity of the tower crane.